Free PMP Certification Mock Exams

pmp

Learning Modes

Practice Mode

Learn with hints and instant feedback.

Exam Mode

Timed testβ€”no hints, real exam feel.

Q&A List

Browse questions with answers.

PMP - Project Management Professionals

PMP - Project Management Professionals

Free PMP Mock Exam #1

Free PMP Mock Exam #1 | 50 free Questions, Answers and Explanations

Free PMP Mock Exam #2

Free PMP Mock Exam #2 | 50 free Questions, Answers and Explanations

Free PMP Mock Exam #3

Free PMP Mock Exam #3 | 50 free Questions, Answers and Explanations

Free PMP Mock Exam #4

Free PMP Mock Exam #4 | 50 free Questions, Answers and Explanations

Free PMP Mock Exam #5

Free PMP Mock Exam #5 | 100 free Questions, Answers and Explanations

Free PMP Mock Exam #6

Free PMP Mock Exam #6 | 100 free Questions, Answers and Explanations

Free PMP Mock Exam #7

Free PMP Mock Exam #7 |100 free Questions, Answers and Explanations

Free PMP Mock Exam #8

Free PMP Mock Exam #8 |100 free Questions, Answers and Explanations

Free PMP Mock Exam #9

Free PMP Mock Exam #9 |100 free Questions, Answers and Explanations

Free PMP Certification Mock Exam Test - Free Questions & Quizzes

PMP Exam Formulas

Formula Name Formula & Explanation
PERT (Program Evaluation and Review Technique) PERT = (P + 4M + O) / 6
  • O = Optimistic estimate
  • M = Most Likely estimate
  • P = Pessimistic estimate
Standard Deviation (SD) SD = (P – O) / 6
  • O = Optimistic estimate
  • P = Pessimistic estimate
Float / Slack Late start – Early start
Late finish – Early finish
Communication Channels n (n-1)/2
  • n = number of team members
Cost Performance Index (CPI) CPI = EV / AC
  • EV = Earned Value
  • AC = Actual Cost
Schedule Performance Index (SPI) SPI = EV / PV
  • EV = Earned Value
  • PV = Planned Value
Cost Variance (CV) CV = EV – AC
  • EV = Earned Value
  • AC = Actual Cost
Schedule Variance (SV) SV = EV – PV
  • EV = Earned Value
  • PV = Planned Value
Estimate At Completion (EAC)
  1. BAC / CPI β€” if CPI remains the same
    • BAC = Budget at completion
    • CPI = Cost performance index
  2. AC + ETC β€” Initial Estimates are flawed
    • AC = Actual Cost
    • ETC = Estimate to Completion
  3. AC + BAC – EV β€” if BAC remains the same
    • AC = Actual Cost
    • BAC = Budget at completion
    • EV = Earned Value
Estimate To Completion (ETC) ETC = EAC – AC
  • EAC = Estimate at Completion
  • AC = Actual Cost
Variance At Completion (VAC) VAC = BAC – EAC
  • BAC = Budget at completion
  • EAC = Estimate at Completion